Project Publishing Failed due to Scheduling Conflict

Filed under: PS 2013 — Tags: — Peter Holpar @ 05:43

Recently we found an issue in the Project Server on the Manage Queue Jobs page in our PWA (http://YourProjectServer/PWA/_layouts/15/pwa/Admin/queue.aspx). A project publishing failed due to an error. The corresponding event log entries are:

PWA:http://YourProjectServer/PWA, ServiceApp:ProjectServerApplication, User:i:0#.w|YourDomain\FarmUser, PSI: SSP: Scheduling failed., LogLevelManager Warning-ulsID:0x38737A33 has no entities explicitly specified.
PWA:
http://YourProjectServer/PWA, ServiceApp:ProjectServerApplication, User:i:0#.w|YourDomain\FarmUser, PSI: Microsoft.Office.Project.Scheduling.EventHorizonFinishException: Error in the application.     at Microsoft.Office.Project.Scheduling.Calendar.NextShift(Int32& day, Int32& shift, RelTimeInterval& interval)     at Microsoft.Office.Project.Scheduling.Allocate.ScheduleForward(IShiftReader shiftReader, AllocationInfo allocationInfo, RelTimeInterval timeIn, IShiftAvailability shiftAvailability, AssignmentWorkList workList, Int64& work, RelTimeInterval& timeOut)     at Microsoft.Office.Project.Scheduling.Allocate.CalendarTimeBetween(IShiftReader shiftReader, RelTimeInterval timeIn, RelTime& duration)     at Microsoft.Office.Project.Scheduling.Allocate.CalendarTimeBetween(IShiftRea…
…der shiftReader, RelTime start, RelTime finish, RelTime& duration)     at Microsoft.Office.Project.Scheduling.SlackUtil.ComputeFinishSlack(Session session, ProjectSchedules projects, Project project, Task task, TaskSchedule taskSchedule, Calendar calendar, Boolean mixedAsapAlap)     at Microsoft.Office.Project.Scheduling.SlackUtil.ScheduleSlack(Session session, ProjectSchedules projects, Project project, Task task, TaskSchedule taskSchedule, Calendar calendar)     at Microsoft.Office.Project.Scheduling.SlackUtil.ScheduleSlack(Session session, ProjectSchedules projects, SchedulingOptions options)     at Microsoft.Office.Project.Scheduling.SessionSchedulerBase.Schedule(SessionSchedule schedule, SchedulingOptions options)     at Microsoft.Office.Project.Scheduling.Scheduler.ScheduleApply(ISch…
…edulingEngineData data, ISchedulingOptions options, SchedulingDataFilter filter)     at Microsoft.Office.Project.Server.BusinessLayer.ProjectSchedule.Schedule(), LogLevelManager Warning-ulsID:0x38737A34 has no entities explicitly specified.
Microsoft.Office.Project.Scheduling.EventHorizonFinishException: Error in the application.     at Microsoft.Office.Project.Scheduling.Calendar.NextShift(Int32& day, Int32& shift, RelTimeInterval& interval)     at Microsoft.Office.Project.Scheduling.Allocate.ScheduleForward(IShiftReader shiftReader, AllocationInfo allocationInfo, RelTimeInterval timeIn, IShiftAvailability shiftAvailability, AssignmentWorkList workList, Int64& work, RelTimeInterval& timeOut)     at Microsoft.Office.Project.Scheduling.Allocate.CalendarTimeBetween(IShiftReader shiftReader, RelTimeInterval timeIn, RelTime& duration)     at Microsoft.Office.Project.Scheduling.Allocate.CalendarTimeBetween(IShiftReader shiftReader, RelTime start, RelTime finish, RelTime& duration)     at Microsoft.Office.Project.Scheduling.SlackU…
…til.ComputeFinishSlack(Session session, ProjectSchedules projects, Project project, Task task, TaskSchedule taskSchedule, Calendar calendar, Boolean mixedAsapAlap)     at Microsoft.Office.Project.Scheduling.SlackUtil.ScheduleSlack(Session session, ProjectSchedules projects, Project project, Task task, TaskSchedule taskSchedule, Calendar calendar)     at Microsoft.Office.Project.Scheduling.SlackUtil.ScheduleSlack(Session session, ProjectSchedules projects, SchedulingOptions options)     at Microsoft.Office.Project.Scheduling.SessionSchedulerBase.Schedule(SessionSchedule schedule, SchedulingOptions options)     at Microsoft.Office.Project.Scheduling.Scheduler.ScheduleApply(ISchedulingEngineData data, ISchedulingOptions options, SchedulingDataFilter filter)     at Microsoft.Office.Project.Ser…
…ver.BusinessLayer.ProjectSchedule.Schedule() StackTrace:  at Microsoft.Office.Project.Server.Native.dll: (sig=134ce9b5-648a-4c93-8b48-a364a0364a09|2|microsoft.office.project.server.native.pdb, offset=3C16) at Microsoft.Office.Project.Server.Native.dll: (offset=1265D)

Opening the project in Project Professional multiple scheduling conflicts were displayed, see the Tooltip, the End field having red underline, the red time-bars on the Gantt-chart on the right and the value of the Warning field on the screenshot below.

image

These conflicts were the result of a failed manual task scheduling. By right-clicking on the task we can either turn off  the manual scheduling for the given task or fix the issue via the Task Inspector. Optionally, you can hide the warning as well, by setting the value of the Ignore Warning field.

After fixing all of the conflicts, the project publishing was successful.

Leave a Comment »

No comments yet.

RSS feed for comments on this post. TrackBack URI

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

Blog at WordPress.com.

%d bloggers like this: